1. Scope Works: Pipeline
Location:
(i) Pipeline route for Sungai Bengkoka Lower and Sungai Togohu.
(ii) Welding of pipe for Sungai Bengkoka Lower and Sungai Togohu.
(iii) Welding of collar joints for Sungai Bengkoka Lower and Sungai Togohu.
Activity:
(i) 180 nos. of pipes of size 2000mm dia. from Kampung Tasik Buyut stockyard delivered to Sungai Bengkoka Lower pipeline route, whilst 80 nos. of pipes (equivalent to 480m) of size 1800mm dia. to Sungai Togohu pipeline route.
(ii) 85 nos. of pipes (equivalent to 510m) were jointed at Sungai Bengkoka Lower pipeline route.
(iii) 18 nos. of pipes (equivalent to 108m) were jointed at Sungai Togohu pipeline route.
2. Scope Works: Access Road
Location:
(i) Access Road at Point L to point O.
Activity:
(i) Concreting works for the access road.
(ii) Laying of gravel and compaction works.
3. Scope Works: Power Houses
Location:
(i) Sungai Bengkoka Lower Power House @Point A1
(ii) Sungai Bengkoka Upper / Sungai Togohu House @Point I1
Activity:
(i) Excavation and breaking of boulders for tailrace at Sungai Bengkoka Lower Power House in progress.
(ii) Prepration of rebar and formwork for ground beam, tailrace slab, tailrace wall at Sungai Bengkoka Lower Power House.
(iii) Concreting works for pad footing and stump at Sungai Bengkoka Upper / Sungai Togohu Power Houses.
(iv) Backfilling for stump and pad footing area.
(v) Application of anti-termite.
(vi) Concreting work for slab.
4. Scope Works: Transmission Line
Activity:
(i) 530 nos. of spun poles for transmission line were delivered to temporary stockyard in Kampung Tasik Buyut.
(ii) 480 nos. of spun poles were delivered and placed at Jalan Mosolog and Jalan Damai,
(iii) Works for digging of holes and planted of poles are on-going. 305 nos. of spun poles planted.
5. Scope Works: Extension of PPU
Activity:
(i) Pile Driving Analyser (“PDA”) Test to micro-piles conducted.